Admin Docket Number : RM77
Date Filed : 06/28/2022

Small Generator Interconnections

No. Subject Date
1 Staff of the Public Service Commission - Petition for Rulemaking-Amendment to the Small Generator Facility Interconnection Regulations COMAR 20.50.02 and 20.50.09 and PC 44 Interconnection Workgroup Phase IV Final Report. PC44 06/23/2022
2 The Commission - Notice Initiating Rulemaking and Directing Workgroups. RM77 06/28/2022
3 Center for Renewables Integration, Inc. - Comments. RM77 07/18/2022
4 Solar Energy Industries Association - Chesapeake Solar and Storage Industries Association - Comments. RM77 07/19/2022
5 Potomac Electric Power Company - Baltimore Gas and Electric Company - Joint Comments. RM77 07/19/2022
6 Office of People's Counsel - Comments. RM77 07/19/2022
7 Staff of the Public Service Commission - Comments. RM77 07/19/2022
8 Interstate Renewable Energy Council, Inc. - Comments. RM77 07/20/2022
9 The Commission - Service List. RM77 08/04/2022
10 The Commission - Minutes from August 2, 2022. Rulemaking Session 164. RM 77. 08/11/2022
11 CRC Salomon, Inc. - Stenographers Record Hearing. Date: August 2, 2022 at 10:00 A.M. RM77 08/17/2022
12 Staff of the Public Service Commission - Comments of the Staff of the Public Service Commission - Revisions to the Code of Maryland Regulations (“COMAR”) 20.50.02.02 and 20.50.09.01, .06, and .14. RM77 01/17/2023
13 The Commission - Notice of Rulemaking Session (Small Generator Facility Interconnection). RM77 01/30/2023
14 The Commission - Minutes from February 22, 2023. Rulemaking Session 170. RM 77 02/22/2023
15 CRC Salomon, Inc. - Stenographers Record Hearing Date. February 22, 2023. 11:35 a.m. RM77 03/09/2023
16 The Potomac Edison Company - Update to Service List. RM77 12/14/2023